Roofing: 

  • Replace near end of life North Cottage roof with EPDM: $37,080 - STARTED

  • Replace near end of life South Cottage roof with EPDM: $37,080 - STARTED

Fire alarms and electronic systems:

  • Currently no Priority One repairs required

HVAC/Plumbing/Electrical infrastructure:

  • Currently no Priority One repairs required

Structural and interior repairs:

  • Remove and replace failing outdoor concrete walking surfaces: $72,960

  • Remove asbestos flooring (VAT) and replace with carpet: $446,760 - STARTED

  • Replace gym ceiling (current gym ceiling falling): $14,520 - STARTED

  • Remove asbestos flooring (VAT) in restrooms and replace with sheet vinyl: $18,600 - STARTED

Parking Lots:

  • Currently no Priority One repairs required