POMONA ELEMENTARY

pomona.JPG

Roofing: 

  • Currently no Priority One repairs required

Fire alarms and electronic systems:

  • Currently no Priority One repairs required

HVAC/Plumbing/Electrical infrastructure:

  • Replace failing HVAC system: $725,280 - STARTED

  • Replace plumbing fixtures and piping and upgrade restrooms to be ADA compliant: $135,360 - STARTED

Structural and interior repairs:

  • Remove and replace failing outdoor concrete walking surfaces: $248,760 - STARTED

  • Install building infrastructure to support new HVAC system: $154,680 - STARTED

  • Remove asbestos flooring (VAT) and replace with carpet: $300,000 - STARTED

  • Replace worn out synthetic gym floor with sports floor: $70,440 - STARTED

  • Repair Cafeteria foundation and replace worn out VCT: $47,400 - STARTED

Parking Lots:

  • Currently no Priority One repairs required