LINCOLN ORCHARD MESA ELEMENTARY

lincoln orchard mesa.JPG

Roofing: 

  • Replace near end of life A Building roof with EPDM: $464,160 - STARTED

  • Replace near end of life B Building roof with EPDM: $218,160 - STARTED

  • Replace near end of life C Building roof with EPDM: $232,080 - STARTED

  • Replace near end of life Cottage roof with EPDM: $37,080 - STARTED

Fire alarms and electronic systems:

  • Currently no Priority One repairs required

HVAC/Plumbing/Electrical infrastructure:

  • Move location of swamp cooler in kitchen (currently placed above serving line, causing issues with food): $48,360 - STARTED

  • Add cooling system to server room (IT and data storage center): $29,040

  • Convert problematic hydroponic piping from 1990 to district standard DX heating/cooling: $38,640

  • Replace obsolete furnaces in cottages with split systems: $87,000 - STARTED

  • Replace obsolete and failing fancoils and evaporation coolers in C Building: $435,120 - STARTED

  • Repair and replace ceilings in order to upgrade HVAC systems: $188,160 - STARTED

  • Replace entire failing HVAC control system: $255,360 - STARTED

  • Replace modular electric power service from main building: $12,600

  • Replace end of life wall packs and sconces for exterior lighting system: $17,400

Structural and interior repairs:

  • Replace worn out exterior doors on E and W buildings with thermal pane units: $34,800 - STARTED

  • Replace worn out exterior doors in preschool: $13,920 - STARTED

  • Refinish vandalized stucco on North and West sides of gym with heavy duty mesh: $58,080 - STARTED

  • Remove asbestos flooring (VAT) and replace carpet: $22,080 - STARTED

  • Install structure to support new HVAC units: $154,680

  • Remove and replace failing outdoor concrete walking surfaces: $39,120

  • Remove asbestos flooring (VAT) and replace with carpet: $22,080 - STARTED

  • Replace failing exterior doors: $114,840 - STARTED

Parking Lots:

  • Add additional ADA parking spaces (currently inadequate): $25,000 - STARTED